Sunday 5 January 2014

Move all object of a layer into the project in ax 2009

There are many ways to take backup of our all development work like in AX 2009 we can copy usr layer and in AX 2012 we can export model we are working.
We can also export all the objects of layer and take backup. but for doing this we need to move all the objects from a layer into the project. Below I am defining how can we do it.
Step 1: Create a new project.
Then open the newly created project.
Step 2: Choose Advanced Filter/Sort from the toolbar.
A new dialog pops up.

project filter in dynamic ax
You can choose grouping of the objects as in the AOT or by user.
Step 3: Select the required objects.
Use the Select button on the dialog to select the objects you require for your project.
We wanna select all AOT objects from a specific layer, so we’ll use the UtilLevel field in the selection criteria.
                                             
From the screenshot you can see that all objects from the USR layer are selected, you can filter more by entrering the criteria you would like to do.

No comments:

Post a Comment